Rule section, topic | § 250.198 – Compliance with documents incorporated by reference |
Question | Do operators have to comply with industry standards that are referenced in the documents incorporated by reference? |
Answer |
Although only standards incorporated by reference are regulatory requirements, at times compliance with such standards calls for satisfaction of other requirements. For example, API standard 53 section 5.2.7 states that “All lines, crosses, valves, and fittings in the choke manifold system and the drill string safety valve shall be constructed from materials meeting applicable requirements of API 5L and API 6A.” Thus, in order to comply with API Standard 53, as incorporated in the regulations, an operator would need to use the applicable items constructed from materials meeting applicable requirements of API 5L and API 6A. |
Rule section, topic | § 250.198 – Updating documents incorporated by reference |
Question | There were many drilling related API standards changed in the past two years (e.g., STD 53, Specifications: 6A, 16A, 16D, 16F). What will be the process to evaluate and potentially require these new editions? |
Answer |
BSEE will continue to evaluate new editions of documents incorporated by reference and, as appropriate, update the incorporated editions of those documents through the rulemaking process. |
Rule section, topic | § 250.413/414 – Reporting surface and downhole mud weights |
Question | Until eWell is revised, which mud weight should be entered in the eWell Casing Information page? |
Answer |
On the casing information page in eWell, you should enter the downhole mud weight until that worksheet is updated to reflect both surface and downhole mud weights. However, you are required to include both surface and downhole mud weights in all other applicable attachments in eWell. |
Rule section, topic | § 250.421/428(c) – Top of Cement as indication of inadequate cement job |
Question | Would BSEE consider a cement job inadequate if the top of cement does not match the approved top of cement? (i.e. if a job meets the cementing regulations in 250.421 and there are no other indications of an inadequate job, but the logged TOC does not meet the proposed TOC?) |
Answer |
The preamble to the final rule states: “[I]f there are any indications of an inadequate cement job, the operator must evaluate the cement job as required in § 250.428.” 84 FR 21934-21935. With respect to that evaluation, the preamble states: “If the operator encounters circumstances that the approved permits do not address (including PE certification), it would be required to submit a revised permit for BSEE approval that would include the PE certification.” 84 FR 21936 (”If an operator encounters circumstances that are not described in an approved permit, such as unplanned lost returns, then a new BSEE approval would be required at that time”). Section 250.428(c) identifies examples of “indication[s] of inadequate cement job,” including “no cement returns…to expected height.” Thus, if the cement job did not go as approved in the permit, including a discrepancy in TOC, then the job is inadequate and further action is required and may require a new PE certification. |
Rule section, topic | § 250.428(d) – Remedial actions |
Question | If the cement evaluation of a drilling casing or liner determines that hydrocarbon zones are not adequately cemented behind the casing or liner, please confirm whether the BSEE District Manager will require as “remedial actions” that the well be perforated and cement squeezed into the un-cemented hydrocarbon zone(s) prior to continuing of drilling operations. If the cement evaluation of a production liner determines that upper hole hydrocarbon zones that are not intended as initial completion intervals are not cemented, please confirm whether the BSEE District Manager will require as “remedial actions” that the well be perforated and cement squeezed into the uncemented hydrocarbon zone(s) prior to initial completion installation/operations. |
Answer |
In line with longstanding regulations and practice, when there is an inadequate cement job, remedial actions will be approved on a case-by-case basis using sound engineering judgment based on specific well conditions. The alterations to section 250.428(d) do not impact BSEE’s existing approach to the identified situations. |
Rule section, topic | § 250.462(d) |
Question | Please define what BSEE considers a “well design change.” Please confirm that slight changes to the established depth of geological horizons, when the well casing setting objectives have not changed, would not qualify as a “well design change.” |
Answer |
Section 250.462(d) requires reevaluation of the operator’s source control and containment equipment if there is a well design change. As explained in the preamble, BSEE requires notification for any well design change, which must be submitted at the time the operator submits a revised permit. 81 FR 25925. This may include, but is not limited to, changes to the pore pressures, fracture gradients, drilling fluid weights, and casing setting depths or casing materials. These parameters may affect the source control and containment capabilities for a particular well and the associated well containment screening tool (WCST). A revised screening tool will need to be submitted in a revised permit if any of the following has changed for the primary or secondary strings analyzed in the WCST:
|
Rule section, topic | § 250.518(e)(3), 250.619(e)(3) |
Question | Is it BSEE’s intention that setting the depth of the production packer as close as practically possible to the perforated interval will allow for future potential work below the packer, including through tubing plugbacks (i.e., future shallower perforations)? |
Answer |
Each production packer setting depth will be evaluated on a case–by-case basis. Each well and situation is unique. It is reasonably possible that BSEE will approve a setting depth for a production packer that will allow for future potential work below the packer. The provisions at §§ 250.518(e)(3) and 250.619(e)(3) do not require that BSEE only approve a setting depth that would preclude future potential work below the packer. The new regulations are not intended to hinder the installation of production equipment by setting a fixed interval length that must be met or to hinder an operator's flexibility to intervene in or manage its well as necessary. During the permit application process, BSEE may request additional information to justify your specified production packer setting depth to ensure that the packer is set as required in these sections to help ensure long-term equipment reliability. The final rule preamble explained that “BSEE wants to ensure that the packer is not set too high, so that, if there is a problem with the packer in the well (e.g., a leak), operators will have enough space above the packer to pump a sufficient volume of weighted fluid into the well to exert a hydrostatic force greater than the force created by the reservoir pressure below the packer.” 81 Fed. Reg. 25888, 25927 (April 29, 2016). |
Rule section, topic | § 250.518(e)(4) and 250.619(e)(4) – Setting packers in cemented intervals |
Question | Please provide clarity on what options are available for setting packers in un-cemented casing. Industry data confirms that setting packers in un-cemented casing is common and safe. (Example - SPAR - Mudline Packer) The requirement to set production packers within the cemented interval of the selected casing section is not always possible. Please confirm that an alternative mean of compliance will be acceptable in lieu of performing any type of remedial cement squeeze. |
Answer |
Requests for departure or alternate compliance to set the packer in an un-cemented casing will be reviewed on a case-by-case basis in connection with the permit. |
Rule section, topic | § 250.712 – Rig move notifications for storms. |
Question | Is the rig move notification required when evading a hurricane / storm in addition to the required eWell submission to the hurricane response team? |
Answer |
Yes, a rig move notification is also required. |
Rule section, topic | § 250.712 – Rig move notifications for storms. |
Question | If an operator secures a well in anticipation of possible need to evade a hurricane but does not actually end up leaving the safe zone, do they need to notify the BSEE District? |
Answer |
BSEE does not require a rig move notification if the rig does not leave the safe zone. However, BSEE requires notification and District approval when putting the well in a safe state before leaving the well, if possible. See 30 CFR 250.720(a). |
Rule section, topic | § 250.724 – Real-time monitoring (RTM) requirements – RTM plans |
Question | Will BSEE enforce the content of the RTM plan? And will BSEE also specify how an operator must comply with the RTM plan requirements (e.g determine the terms "significant and/or prolonged"; listing what data is monitored; and length/timing of RTM data)? |
Answer |
BSEE has outlined the minimum RTM and RTM plan requirements in the regulations. Since the 2016 Rule, the RTM planning requirements have been designed to be “flexible, performance-based measures that better reflect BSEE’s intention that operators use RTM as a tool to improve their own ability to prevent well control incidents while providing BSEE with sufficient access to RTM information to evaluate system improvements.” 2016 final rule preamble, 81 FR 25897; see also 2019 final rule preamble, 84 FR 21942 (“The 2016 WCR’s RTM requirements were themselves largely performance-based, relying primarily on the operator’s development of an RTM plan tailored to its operations but built off of core principles. The revisions implemented here do not reflect a sea change in philosophy…”). With respect to enforcement, the final rule preamble states: “This regulation requires that operators develop and implement RTM plans, and specifically requires that those plans be made available to BSEE upon request. If BSEE has any concerns with an operator’s RTM operations, then BSEE may undertake inspections and enforcement actions to ensure compliance with the regulations. BSEE has additional options such as routine onsite inspections or verifications through the permitting process to ensure that RTM plans are implemented in compliance with the regulations.” 84 FR 21943. The regulations since 2016 have required that operators both “develop and implement” RTM plans. 30 CFR 250.724(c) (emphasis added). These principles are unchanged in this rulemaking. As a general principle, BSEE considers the term “significant and/or prolonged” loss of RTM capability as a period of time “that potentially could increase the risk of a well-control event.” 2016 final rule preamble, 81 FR 25938. “BSEE did not intend that proposed requirement to apply to minor or routine interruptions in RTM capabilities that pose no significant risk to safety or of a LWC.” 2016 final rule preamble, 81 FR 25897. This regulation is not prescriptive and thus does not establish an express time period. An operator should use its ordinary prudence and industry expertise to establish in its RTM plan which losses of RTM capability should be characterized as “significant and/or prolonged,” taking into account the prior BSEE descriptions. Although it is generally the operator’s responsibility to initially define in its plan which losses of RTM capability will be considered “significant and/or prolonged” based on the facts associated with the RTM system’s interruption, BSEE would typically expect that a reasonably prudent operator would take action under its plan pursuant to 250.724(c)(6) if that operator loses any real-time monitoring capabilities for a 24 hour period. |
Rule section, topic | § 250.724 – Real-time monitoring (RTM) requirements – RTM personnel |
Question | Is RTM personnel separate from rig personnel, meaning that no person on the rig could perform RTM functions? |
Answer |
The rig personnel should not be considered “monitoring personnel” for purposes of the RTM planning requirements at 250.724(c)(5) and (6) furthermore, rig personnel and RTM personnel should be in separate locations for a given well. The final rule preamble clarifies: “BSEE requires the rig personnel and monitoring personnel to be separate individuals.” 84 FR 21943. The operator is not precluded from having personnel on the rig performing real-time monitoring functions, but those individuals may not serve as the “monitoring personnel” required by regulation. BSEE requires the operator to identify in the RTM plan how the RTM data will be transmitted and monitored, requires the rig personnel and monitoring personnel to be separate individuals, and requires certain communication capabilities among personnel, but does not prescriptively dictate the establishment of an onshore monitoring center, or even require that monitoring personnel must be onshore. See, e.g., 84 FR 21942. As noted in the preamble, “[w]ith currently available technology, operators are capable of using RTM remotely on computers and tablets using web based applications. This allows for subject matter experts to utilize the data anywhere and at any time as necessary, as detailed in the company’s RTM plan.” Id. |
Rule section, topic | § 250.724 – Real-time monitoring (RTM) and previously approved permits |
Question | Will new permit applications be required to be filed after April 29, 2019, or can operations continue under previously- approved permits? |
Answer |
BSEE regulations apply, as of their effective date(s), to all operations conducted under a lease. Operations conducted after the effective date of this regulation (April 30, 2019) may proceed on the basis of a previously-approved permit if those operations are conducted in accordance with both the approved permit and the applicable regulatory requirements in effect on the date the operations are conducted. BSEE does not require that an operator submit a new permit application in those circumstances simply because the new requirements have taken effect. However, if compliance with applicable regulatory requirements would require material modifications to your operations that would place them outside the terms of the approved permit, you would be required to submit a new or modified permit application that demonstrates that your operations will be completed in accordance with the newly effective regulatory requirements |
Rule section, topic | § 250.724 – Real-time monitoring (RTM) for certain rig unit types |
Question | Do the RTM requirements apply to hydraulic work over units or snubbing units? |
Answer |
No, This requirement does not extend to hydraulic work over units or snubbing units used on the same vessel or facility. |
Rule section, topic | § 250.724 – Proposed revisions to 2016 WCR RTM |
Question | Given that the 2018 Proposed Well Control Rule Revisions proposed to alter the requirements for real-time monitoring, but no Final Rule has yet been published, what options, if any, are available to obtain approval of alternate approaches toward the real-time monitoring provisions? |
Answer |
Pursuant to the longstanding regulatory provision at 30 CFR 250.141, you may submit a request to use alternate procedures or equipment that meet the required standards. |
Rule section, topic | § 250.730(a) – Multi-purpose service vessels |
Question | Please confirm that the well control rule requirements do not apply to Multi-Purpose Service Vessels (MSV) performing well work through subsea tree and through tubing intervention operations. |
Answer |
The cited regulation does apply to such operations. Section 250.730(a) is applicable to all BOP systems and system components, and is not specific to the type of rig unit. A regulation’s incorporation of an industry standard extends requirements only to the subject matter covered by the incorporated standard. 250.730 applies to BOP systems and system components and incorporates Standard 53. API Standard 53 states, “BOPs are not: gate valves, workover/ intervention control packages, subsea shut‐in devices, well control components (per API 16ST), intervention control packages, diverters, rotating heads, rotating circulating devices, capping stacks, snubbing or stripping packages, or nonsealing rams.” This paragraph applies to intervention units which utilize BOP systems. |
Rule section, topic | § 250.730(a)(2) – API Spec 17D |
Question | What specifically from 17D is BSEE wanting applied to BOPs? 17D is a subsea production tree standard. |
Answer |
API standard 53 includes normative references to API Spec 17D. Accordingly, Spec 17D should be followed as necessary to achieve compliance with API standard 53. |
Rule section, topic | § 250.730(a)(3) |
Question | It is industry’s interpretation that the control system required by § 250.730(a)(3) must have the regulated range to shut in under MASP conditions and procedures in place to secure the well under those circumstances. Standard operating practice is to maintain the BOP manifold regulator setting at 1500 psig, as there are other functions that share this regulator. Note, the emergency shear ram functions are activated by a separate high pressure shear circuit, while the pipe and variable bore ram functions are controlled by a regulated, lower pressure circuit. Question – Is it acceptable to have the ability to increase the regulated pressure if required? |
Answer |
Yes, the ability to increase the regulated pressure when required is acceptable under § 250.730(a)(3). The regulation does not prescribe any specific requirements for regulator settings, and BSEE requires only that the regulator settings function as designed and as specified in the approved APD. 81 Fed. Reg. 25941. |
Rule section, topic | § 250.730(a)(3) – Pipe and variable bore ram sealing requirements |
Question | Industry interprets § 250.730(a)(3) to be a pipe and variable bore ram design requirement, such that, between all of the pipe and variable bore rams installed, the BOP stack will be capable of effectively closing and sealing on any drill pipe, work string, and tubing in the hole under MASP. Is that correct? |
Answer |
That is correct. |
Rule section, topic | § 250.730(b) – OEM training recommendations |
Question | In situations where there are training gaps (e.g., new personnel are hired, or personnel are promoted) will there be a grace period for completing the training related to courses that have limited availability? Will a lead supervisor comply with the overall training criteria for personnel who must be trained to meet or exceed all OEM recommended training while non-supervisory personnel continue to work on the safety and environmental systems (SEMS), on the job training (OJT), and original equipment manufacturer (OEM) training courses as part of their development? |
Answer |
The regulation contains no grace period for completing training related to courses that have limited availability. The regulation states that all maintenance and repair personnel who work on a BOP system must meet or exceed any OEM training recommendations (unless otherwise directed by BSEE). Personnel who are receiving on the job training may work with trained personnel in performing specific activities. However, trained personnel must be present and be providing direct oversight over any work that is performed. |
Rule section, topic | § 250.730(c) |
Question | What type of failure data should be reported to BSEE and how should it be submitted? |
Answer |
BSEE is currently working with the industry to ensure that the terminology, data, and content for failure reporting information is consistent with the existing data reporting systems that are currently being used within a large part of the industry. We believe that consistent reporting processes and formats will facilitate other sharing of data across the industry. BSEE will also be providing operators with the option of reporting information directly to the SAFEOCS reporting system through the Bureau of Transportation Statistics (BTS). BTS is currently ensuring that the systems and processes are in place to accept this type of data directly from operators. BSEE will be issuing specific guidance on these issues in the next several weeks. Until this process is fully operational, operators should use one of the following options to report failures: Download the BOP Component Failure Form from the SafeOCS website (www.safeocs.gov) and submit it electronically directly to BSEE at BOPFailure@BSEE.gov. The form will be available on July 28, 2016. |
Rule section, topic | § 250.730(c)- BOP Failure reporting |
Question | When does the BOP equipment failure reporting start? After stump test, during stump test? Is this only required on the BOP that is in use for rigs that have 2 BOP stacks? |
Answer |
The failure reporting requirements for the BOP equipment are triggered when the rig is on site and includes all BOP stacks and any issues discovered during any testing or maintenance. |
Rule section, topic | § 250.731- Submittal of information if a rig moves off a well |
Question | Will BSEE require the information that must be submitted when a facility moves off of a well to be submitted in the case of temporary “moves” due to weather or installation of subsea equipment, etc.? |
Answer |
Section 250.731 requires that you submit updated information in your next submittal if a rig has moved off location from the well (due to a storm or for any other reason). For example, the information listed in § 250.731 must be updated (or confirmed still to be accurate) and submitted with an APD, APM, or other necessary submittal when the rig moves back onto the well. Also, if a rig has moved off location (due to a storm or for any other reason), you must follow the rig movement reporting requirements according to § 250.712. If operations are suspended to make repairs or changes to any part of the subsea BOP system, you must also follow the requirements of § 250.734(b). |
Rule section, topic | § 250.731(b) – Schematic drawings |
Question | Please provide details on what is required to satisfy the schematic drawing requirements of paragraphs (b)(3) and (b)(8). Please clarify what is specifically required: Schematics or Process and Instrumentation Diagrams? |
Answer |
The regulation requires the submission of schematic drawings for compliance with both paragraphs (b)(3) and (b)(8). This requirement is consistent with prior regulations (see, e.g., former §§ 250.416(d); 250.515(b); 250.615(b)), including specifically the requirement to include the location of associated valves on your BOP drawings. |
Rule section, topic | § 250.731(c)(2)- Maximum environmental and operational conditions |
Question | Does maximum anticipated surface pressure (MASP) on surface BOP equipment and Maximum anticipated wellhead pressure (MAWHP) for Subsea BOP equipment qualify as the most extreme load case for “environmental conditions”? |
Answer |
The rule refers to “the maximum environmental and operational conditions anticipated to occur at the well.” The regulations do not address the “most extreme load case.” For purposes of identifying maximum anticipated pressures, the definitions of MASP and MAWHP set forth in API Standard 53 are sufficient. However, the Independent third party must also take into account the specific environmental and operational conditions at the well (e.g., temperature and H2S). As BSEE explained in the final rule preamble, in order to assess these well conditions, operators should rely on “reasonably predictable, site-specific conditions instead of hypothetical worst-case conditions.” 81 Fed. Reg. 25946 (April 29, 2016). MASP for surface BOPs and MAWHP for subsea BOPs would ordinarily reflect reasonably predictable, site-specific conditions on which a certification pursuant to section 250.732(c)(2) may be based. |
Rule section, topic | § 250.732(a)(1)(ii) – Generally accepted quality assurance standards |
Question | Please confirm that shear testing performed by facilities that test pursuant to API Standards and/or Recommended Practices satisfies the “generally accepted quality assurance standards” requirement. |
Answer |
Section 250.732(a)(1)(ii) is performance-based so as to give operators the flexibility to use testing facilities that meet generally accepted quality assurance standards. BSEE believes that operators are capable of identifying such standards. These might include API standards, depending on the content of those documents. |
Rule section, topic | § 250.732(a)(1)(iv) and 250.734(a)(16)(i) – Shear testing on the outermost edges of the shearing blades |
Question | Will BSEE accept API 16A PR2 test data for verification of the rams meeting this requirement? |
Answer |
BSEE regulations do not currently incorporate API 16A PR2. However, BSEE will continue to evaluate this standard for future incorporation into the regulations and continue to work with OEMs for improved ways to demonstrate testing on the outermost edges of the shearing blades. BSEE currently has no general position with respect to whether API 16A PR2 test data satisfies the regulatory requirement to submit verification and documentation that shear testing was performed on the outermost edges of the shearing blades of the shear ram, and will evaluate submitted documentation within the permit to ensure this requirement is met. |
Rule section, topic | § 250.732(a)(3) – Shearing and sealing pressures |
Question | The shearing pressure is pipe dependent while the sealing pressure requirement is a function of the operator and ram and is independent of the pipe size and material properties. Industry’s interpretation of the sealing pressure is the Minimum Operator Pressure For Low Pressure Seal (MOPFLPS) plus correction for MASP and hydrostatic effects. |
Answer |
It is the operator’s responsibility to determine how the sealing pressure calculations are applied to specific components. According to the requirements of 250.732(a)(3), it is the responsibility of the independent third party to validate and certify shearing and sealing capabilities of the BOP. |
Rule section, topic | § 250.732(c)(2) – Third party verification |
Question | Can you please clarify that compliance with the appropriate specification (API 16A, API 16C, etc.,) supported by the current additional requirements of ABS, DNV.GL, etc., meet your intent for design verification? |
Answer |
This regulation is performance-based and provides operators with the flexibility to demonstrate the sufficiency of the design. In some cases, compliance with the specification and third party requirements may be sufficient to satisfy this provision. |
Rule section, topic | § 250.732(c)(2) – Design testing |
Question | Is certification that equipment is designed and tested per API Standards sufficient to meet these requirements? |
Answer |
This paragraph sets general, performance-based requirements and is intended to be broad enough to provide flexibility in verifying the performance and reliability of the component and system designs without expressly requiring conformance to any specific standard. These might include design and testing in accordance with API standards to meet the design verification requirements of 250.732(c)(2), depending on the content of those documents. |
Rule section, topic | § 250.732(c)(4) – Independent third party presence during manufacturing |
Question | Does this section imply that the Independent 3rd party must attend all aspects of the manufacturing including the selection and approval of raw materials? Does this also apply to vendor supplied off the shelf items? |
Answer |
The independent third party must conduct a comprehensive review of the BOP system and related equipment. BSEE requires an operator to provide the independent third party access to any facility associated with the BOP system or related equipment during the review process. The independent third party must verify that the fabrication and manufacture processes used recognized engineering practices and quality control and assurance mechanisms. However, this does not require the independent third party to be physically present during fabrication or manufacturing. BSEE does not specify how the independent third party must obtain the information necessary to provide the required verifications. |
Rule section, topic | § 250.732(d)(5) – SEMS information |
Question | SEMS regulations currently require 3 year audits. The wording within §250.732(d)(5) appears to suggest an annual SEMS audit. Is BSEE’s intent to require a full SEMS audit annually, above and beyond the current SEMS regulations? |
Answer |
Section 250.732(d)(5) does not require a full SEMS audit annually. This paragraph requires verification that the mechanical integrity provisions of the SEMS plan, related to specific equipment, have been implemented. This is process is different than the audit of the entire management system across all operations that is typically performed every three years. |
Rule section, topic | § 250.733(b)(2) – Risers |
Question | The preamble that was published with the final rule states that “the final rule does not require that operators change the riser configuration for risers that were installed on floating facilities before 90 days after the publication date of the final rule.” Please confirm that the repositioning of a presently installed Dual Casing Riser (DCR) on a floating facility from an existing well to another well will not constitute an “installation” such that the DCR will lose the “grandfathered” status that is granted in the preamble. |
Answer |
Merely repositioning a riser within the same existing floating facility, for example, from one well to another on the same facility, would not constitute the “installation” of a riser that would otherwise require use of a dual bore riser configuration under § 250.733(b)(2). |
Rule section, topic | § 250.733(b)(1); 250.734(a)(1); 250.734(a)(1)(ii); 250.734(a)(3)(i); 250.734(a)(3)(ii); 250.734(a)(3)(iii); 250.734(a)(6)(i); 250.734(a)(6)(ii); 250.734(a)(6)(iii); 250.734(a)(6)(iv); 250.734(a)(6)(v) |
Question | Do all of the dual shear ram regulations fall under the 5 year compliance timeframe (e.g., the subsea accumulator capacity for the dual shear ram)? |
Answer |
30 CFR 250.734(a)(1) requires use of dual shear rams on subsea BOPs no later than April 29, 2021. 30 CFR 250.733(b)(1) requires that surface BOPs on new floating production facilities installed after April 29, 2021, comply with the regulatory requirements in § 250.734(a)(1), including the requirement to use dual shear rams. The 2019 final rule establishes numerous equipment and process requirements that are ancillary to the operation of dual shear rams as well as to other types of rams and other components of subsea BOPs. For example, § 250.734(a)(3)(i) requires that each subsea BOP have sufficient subsea accumulator capacity to close each required shear ram, one pipe ram, and ram locks, and to disconnect the LMRP. BSEE intended such ancillary requirements to take effect at the same time as the requirements for installation or availability of the specific equipment or component that the ancillary equipment or process is designed to operate. So, for example, the accumulator capacity closure requirement of § 250.734(a)(3)(i) must be met by April 29, 2021. The following provisions of the final rule also fall under the dual shear rams requirements; therefore, with regard to operating the dual shear rams, you must comply with these requirements by the April 29, 2021, compliance date:
|
Rule section, topic | § 250.734(a) – Dual shear rams |
Question | Does the regulation require that the shear rams be identical and have identical capacities? |
Answer |
No, the regulations do not require identical shear rams. 30 CFR 250.734(a)(ii) requires that both shear rams (i.e., each shear ram) be capable of performing the entire range of listed shearing operations. However, the regulation only requires that at least one shear ram be capable of closing and sealing the wellbore after shearing under MASP. |
Rule section, topic | § 734(a)(1) – Dual shear rams |
Question | For rigs that already are configured with dual shear rams, must they comply with the requirement that both shear rams be capable of shearing the newly added component of "appropriate area for the liner or casing landing string" prior to April 29, 2021? |
Answer |
You are not required to have a second shear ram with the identified capabilities until April 29, 2021. Operators are not prohibited from meeting the dual ram shearing requirements prior to 2021, and BSEE encourages operators to pursue continual improvement toward these standards. |
Rule section, topic | § 250.734(a)(1)(ii) – Both shear rams must be capable of shearing at any point along the tubular body of any drill pipe (excluding tool joints, bottom-hole tools, and bottom hole assemblies such as heavy-weight pipe or collars), workstring, tubing and associated exterior control lines, appropriate area for the liner or casing landing string, shear sub on subsea test tree, and any electric-, wire-, slick-line in the hole; under MASP. At least one shear ram must be capable of sealing the wellbore after shearing under MASP conditions as defined for the operation. Any non-sealing shear ram(s) must be installed below a sealing shear ram(s). |
Question |
Do the requirements in 30 CFR 250.734(a)(1)(ii) have to be met regardless of what tubulars are being used in the well? Example: If wireline/slick line is not going to be run, no requirement to have a shear ram that can shear/cut the wire line to be installed in the BOP. |
Answer |
Effective April 29, 2019, both shear rams are required be able to perform the shearing operations that may be necessary during your planned operations. For example, if you do not plan to run wireline during your operations, then the shear rams do not need to be capable of shearing wireline. While not required, BSEE recommends that all BOP shear rams be capable of performing the entire range of listed shearing operations in case of emergency. |
Rule section, topic | § 250.734(a)(1)(ii) – Shearing casing |
Question | The shearing of “appropriate area for the liner or casing landing string” is not intended to mean any part or portion of the actual liner or actual casing string? |
Answer |
Correct, the appropriate area for the liner or casing landing string is the portion of the string that will be across the stack once landed in the wellhead which may include the running tool. |
Rule section, topic | § 250.734(a)(1)(ii) – Dual shear ram requirement |
Question | Will BSEE accept applications with alternate compliance for special configurations (e.g. allow one BSR and one CSR)? Will BSEE continue to accept a configuration on rigs with three shear functions in which the dual-deadman is set up to close one BSR and the CSR? |
Answer |
All subsea BOPs and surface BOPs on new floating production facilities will need to comply with the dual ram requirement by April 29, 2021. All shearing components utilized within the autoshear/deadman systems must meet all required shearing capabilities, regardless of configuration. The regulations have long provided operators the option of seeking approval of alternate procedures or equipment from those required by regulation; such proposals must demonstrate “a level of safety and environmental protection that equals or surpasses current BSEE requirements.” 30 CFR 250.141. BSEE will consider such requests on a case-by-case basis. |
Rule section, topic | § 250.734(a)(6) – Autoshear/deadman functions and an EDS mode |
Question | Does the requirement that “autoshear/deadman functions and an EDS mode must close, at a minimum, two shear rams in sequence and be capable of performing their shearing and sealing action under MASP conditions as defined for the operation” mean that the accumulator system is required to have sufficient volume to provide shearing pressure under MASP when the second ram in the sequence reaches the end of its stroke? |
Answer |
Yes, both rams in the emergency sequence must have the capability to shear under MASP independently, with one being able to seal. There must be enough total volume for each ram to function independently. |
Rule section, topic | § 250.734(a)(6)(ii) – Deadman criteria for activation |
Question | Is there a definition for “signal transmission capacity”? |
Answer |
This is defined as a simultaneous absence of hydraulic supply and control of both subsea control pods. |
Rule section, topic | § 250.734(a)(7) – Acoustic system |
Question | Is the acoustic system required to operate the critical functions listed in 250.734(a)(3)(i) or does it only have to comply with API Standard 53? |
Answer |
BSEE expects an acoustic system to comply with API standard 53. The acoustic system is not required to undertake the operations listed in § 734(a)(3)(i). In addition, if an operator chooses to use an acoustic control system as an additional emergency control measure (in addition to the required autoshear, deadman and EDS systems), the operator must demonstrate that the system is functional. 81 Fed. Reg. 25960. |
Rule section, topic | § 250.735(g)(2)(i) – Remotely-operated locking devices for surface BOP BSRs |
Question | Will new permit applications be required to be filed after April 29, 2019, or can operations continue under previously- approved permits? |
Answer |
BSEE regulations apply, as of their effective date(s), to all operations conducted under a lease. Operations conducted after the effective date of this regulation (April 30, 2019) may proceed on the basis of a previously-approved permit if those operations are conducted in accordance with both the approved permit and the applicable regulatory requirements in effect on the date the operations are conducted. BSEE does not require that an operator submit a new permit application in those circumstances simply because the new requirements have taken effect. However, if compliance with applicable regulatory requirements would require material modifications to your operations that would place them outside the terms of the approved permit, you would be required to submit a new or modified permit application that demonstrates that your operations will be completed in accordance with the newly effective regulatory requirements. |
Rule section, topic | § 250.735(g)(2)(i) – Remotely-operated locking devices for surface BOP BSRs |
Question | Do the remotely-operated locking device requirements apply to hydraulic work over units and snubbing units? |
Answer |
No, as stated in 250.724(a), the requirements apply when conducting well operations with a subsea BOP or with a surface BOP on a floating facility, or when operating in a high pressure high temperature (HPHT) environment. The certification requirement in 250.724(b) is separate from the substantive compliance obligations and does not narrow their scope. |
Rule section, topic | § 250.736(b) and (c) |
Question | Basically, API Standard 53 allows for choke manifolds to be comprised of components of different pressure ratings. Specifically, the upstream portion of the manifold is to be rated equal to the BOP and the downstream portion can be a lower pressure rating. For what part of the choke manifold system does BSEE allow the use of a lower pressure rating than the rated working pressure (RWP)? |
Answer |
BSEE does not consider equipment downstream of the choke isolation valve to be choke manifold components for purposes of 30 CFR 250.736(b). Accordingly, such equipment may have a lower pressure rating that the RWP, as described in API Standard 53. |
Rule section, topic | § 250.737 - BOP testing requirements |
Question | Please confirm that all shear rams in place to comply with the WCR shear requirements of § 250.734(a)(1)(ii) will have to meet the requirements of function testing and pressure testing of § 250.737 by April 29, 2021. |
Answer |
Correct, both shear rams must meet the function testing and pressure testing requirements in 30 CFR 250.737 by April 29, 2021. |
Rule section, topic | § 250.737(a)(5) - The District Manager may require more frequent testing if conditions or your BOP performance warrant |
Question | Please list what “conditions” or “BOP performance” warrant more frequent testing? |
Answer |
As described in the preamble to the final rule, “[this provision] is intended to give District Managers the necessary flexibility and discretion to require [BOP system tests] as needed in specific cases to fulfill the purposes of the regulation.” 81 Fed. Reg. 25966 (April 29, 2016). BSEE will evaluate the specific conditions and BOP performance on a case-by-case basis (e.g., specific well conditions, operations, or equipment) to determine whether to require more frequent testing. This approach – reflected in provisions throughout Part 250 – is essential to provide the flexibility and discretion necessary to ensure that the purposes of the regulations are fulfilled in specific cases. This language is identical to the longstanding language found at former section § 250.447(b), and BSEE is unaware of any significant concerns raised by operators in connection with the District Managers’ exercise of this authority. |
Rule section, topic | § 250.737(c) – Chart range |
Question | Can the low pressure test and high pressure test be on separate charts in order to comply with being within the middle half of the chart range? Or do both tests need to be on the same chart to show the increase in pressure from low to high? |
Answer |
These tests should be on the same chart to show that the transition from low to high happened immediately after conducting the low pressure test; however, two charts can be run simultaneously to prove the low pressure test was conducted before the high pressure test. |
Rule section, topic | § 250.250.737(c) |
Question | Does the recorded test pressures within the middle half of the chart range apply to the high and low pressure tests? |
Answer |
This applies to the high and low pressure test. |
Rule section, topic | § 250.737(d)(5)(ii) – Control panel testing |
Question | Some subsea BOP control systems have a tertiary maintenance panel (often designated as CCU or Subsea Engineers Panel) which is not limited in functionality, but does permit critical operational and safety interlocks to be overridden. These panels are typically not functioned while subsea to mitigate risk of unintended sequence of operations. Can BSEE confirm it is not their intent to include these panels in the subsea function testing requirements? |
Answer |
All BOP panels must be functioned prior to deployment, as stated in API Standard 53 section 7.6.5.1.2. The remote BOP panels that do not have full functionality are required to be function-tested upon the initial BOP tests. Furthermore, these panels do not need to be tested on a monthly basis |
Rule section, topic | § 250.737(d)(12) | |
Question | The deadman accumulator final pressure reading, successful post-firing pressure test and proper ram ‘open’ function gallon counts are positive indicators of a successful test. Please confirm that BSEE would accept these criteria as sufficient in lieu of reducing system reliability for this upgrade? If not, please clarify the Agency’s expectations. | |
Answer |
|
Rule section, topic | § 250.738(a) BOP does not hold required pressure during testing |
Question | Does this requirement begin upon deployment of the stack in service, and would it ever apply to a secondary stack? |
Answer |
This regulation applies upon initial test. For subsea BOPs (primary and secondary) this applies beginning with stump testing, and for surface BOPs this applies upon initial test once rigged up to the well. |
Rule section, topic | § 250.738(d) – Pod or control station failure |
Question | Does any failure of any component whether critical or secondary within the control system result in a BOP pull from the seabed? |
Answer |
If a failure of a component or group of components, whether critical or secondary, renders a control pod non-functional, you must suspend operations in accordance with § 250.737(d)(8). If there are any problems or irregularities, including any leaks, you must contact the appropriate District Manager. The need to recover BOPs for repairs will be determined on a case by case basis. |
Rule section, topic | § 250.738(o) – redundant components |
Question | Please confirm that BSEE would accept an operator’s submission of a risk-based evaluation of all redundant components and pre-determine the conditions that would allow continued operation for a failed redundant component as long as the BOP system still conformed to API Standard 53. Please confirm that BSEE will grant a waiver to allow this pre-determination of actions in advance of starting a well to minimize the suspension of operations. |
Answer |
No. Any redundant equipment failures must be reported as described in this regulation. As BSEE explained in the preamble to the final rule: “If redundant components are installed and planned to be used as necessary, they need to be able to fully function and operate (similarly to the required components) as intended.” 81 Fed. Reg. at 25970. BSEE will evaluate redundant equipment failure reports it receives and evaluate the materiality of an operator’s redundant equipment failure. Requests to operate with failed redundant components will be considered on a case- by-case basis at the time in which the component fails. |
Rule section, topic | § 250.739(b) – 5 year major inspection |
Question | Does the 5 year period run from the time of the last inspection which would comply with the standards of the regulation? |
Answer |
This complete breakdown and inspection must be performed every five years from the latest of the following dates: (1) The date the equipment owner accepts delivery of a new build drilling rig with a new BOP system; (2) The date the new, repaired, or remanufactured equipment is initially installed into the system; or (3) The date of the last five-year inspection conducted on the relevant component. |
Rule section, topic | § 250.739(b) – Condition-based maintenance |
Question | Does BSEE allow for condition-based maintenance instead of the 5 year complete breakdown and physical inspection? |
Answer |
No, a major, detailed inspection must be completed every 5 years. BSEE will review condition-based maintenance as a possible alternative when more data is available. |
Rule section, topic | § 250.739(c) – Visual Inspections | |
Question | When using a surface BOP stack on a floating facility and working through the production riser, are you required to visually inspect the production riser every three days? | |
Answer |
|